Project Name Year Beneficiary Cost
Construction of water resources office in Neel 2005 Ministry of Water Resources - Babil 66,993,836 IQD
Rehabilitation of south drainege in Musaib project 2007 Ministry of Water Resources - Babil 1,164,366 $
Treat of erosion of 800 m from Shatt Al Arab right shore 2007 Ministry of Water Resources - Basra 1,293,950,000 IQD
Treat of erosion of 1200 m from Shatt Al Arab south shore 2007 Ministry of Water Resources - Basra 1,668,275,000 IQD
Rehabilitation of Al Chibaish (construction of three cars Bridges) 2007 Ministry of Water Resources - Thi Qar 1,617,019,000 IQD
Rehabilitation of Thuraima irrigation project in Dewaniya 2008 Ministry of Water Resources - Diwaniya 937,776,000 IQD
Construction of water Gate and Box Culvert For Rufaee river 2008 Ministry of Water Resources - Diwaniya 245,885,000 IQD
Pavement of the main road in Al Thahab Al Abiad valage in Abu Ghraib 2008 Baghdad Governorate 381,500,000 IQD
Execute of a roads network in Al Thahab Al Abiad valege in Abu Ghraib 2008 Baghdad Governorate 1,360,000,000 IQD
Treat of erosion of 800 m from Shatt Al Arab north shore 2008 Ministry of Water Resources - Basra 1,106,538,000 IQD
Pavement of roads in Al Ayaff valege in Madaen 2009 Baghdad Governorate 724,865,000 IQD
Pavement of Kewaiteen street in Aqarqoof / Abu Ghraib 2009 Baghdad Governorate 396,000,000 IQD
Fill with a sub-base layer for a group of roads in Adel Hirat region / Abu Ghraib 2009 Baghdad Governorate 369,000,000 IQD
Supply and pave of stone and build a wall for anti - flood dams project of Wasit thermal power stati 2009 Ministry of Water Resources - Wasit 2,002,860,000 IQD
Lining of Al Qargooliya canal / second stage 2009 Ministry of Water Resources - Baghdad 1,055,596 $
Excavation of east Al Gharf drainage project from 147 km to 170 km 2009 Ministry of Water Resources - Wasit 906,250,000 IQD
Rehabilitation of Kani Shireen Canal 2009 Ministry of Water Resources - Duhok 555,407 $
Complementation of Lateefiya Irrigation Project 2010 Ministry of Water Resources - Baghdad 2,604,797,500 IQD
Several Works in Zubaidi Gutter within Musaib Project 2010 Ministry of Water Resources - Babil 178,227,600 IQD
Construction of 14 Water Culverts in Karbala 2010 Ministry of Water Resources - Karbala 184,169,000 IQD
Excute of Rain Water Drainage Network and Leveling, Filling with Sub-base and Pavement for Rusafa Mi 2010 Ministry of Trading - Baghdad 588,625,000 IQD
Construction of Water Calvert on Abood Al Gharbi / Al Madaen 2010 Ministry of Water Resources - Baghdad 200,590,000 IQD
Finishing Works for Serving Buildings of Om Al Tubool Mosque 2011 Sunni Endowment - Baghdad 4,720,080,000 IQD
Several Works in Zubaidi Gutter within Musaib Project / stage 2 2011 Ministry of Water Resources - Babil 275,128,000 IQD
Ein Al-Tamor Piping Irrigation Project 2012 Ministry of water resources 504,920,000 IQD
Construction of Chamber and Connecting of Electrical Current to Pumps in Ein Al-Tamor 2012 Karbala Governorate 217,796,000 IQD
Treatment of Erosion in Left Side for Euphrates in Al-Hashimiat 2012 Ministry of water resources 399,140,000 IQD
Construction of Roads in Sainekh / Basra 2013 Basra Governorate 519,900,000 IQD
Maintenance of the Service Road for the Strategic Line from 200 km to 220 km 2013 Oil Ministry 1,245,800,000 IQD
Maintenance of the Service Road for the Strategic Line from 200 km to 220 km 2013 Oil Ministry 2,547,600,000 IQD
Implementation of Basra Water Directorate building / the first stage 2015 Basra Governorate 2,199,555,000 IQD
Erosion Treatment occurring on the left side of the Euphrates River in Al-Shinafiyah 2013 وزارة الموارد المائية 1,124,444,000 IQD
Project of improve and develop the electrical network in Naim and Moza area 2013 Baghdad governorate 799,900,000 IQD
Contracting to connect the electrical current to the Al-Tahadi neighborhood 2013 Holy Karbala governorate 1,109,457,500 IQD
Maintenance of the old Kabbasi Bridge and the construction Al-Ajrawiya North Road 2013 Baghdad governorate 2,964,450,000 IQD
Project for the reconstruction of Al-Zubair district mosques in Basra 2013 The Sunni Endowment 354,947,000 IQD
Treatment of the left shoulder of the Tigris River near the two-storey bridge, with a length of 400 2014 Ministry of water resources 745,613,000 IQD
Execution of the earthworks for the ramps of the bridge overpass at the station (610 + 3) km for the 2014 Hammurabi General Co. for Construction Contracting 420,000,000 IQD
Execution of the earthworks for the ramps of the overpass bridge for the highway traffic project R6 2014 Hammurabi General Co. for Construction Contracting 420,000,000 IQD
Contract of delivery the electric current to the Al-Wafaa neighborhood 2014 Holy Karbala governorate 354,947,000 IQD
Treatment of erosion occurring in the Tigris River from km (600 + 49) to km (600 + 50) Al-Madain 2014 Ministry of water resources 2,164,780,000 IQD
Contract of delivery the electric current to the Al-Intifada neighborhood 2014 Holy Karbala governorate 603,278,975 IQD
Implementation of the electrical network of Al-Muheet area and Baghdad Street 2014 Holy Karbala governorate 444,482,500 IQD
Preparing and checking spare materials in the Karbala Electricity Distribution Directorate 2014 Holy Karbala governorate 1,937,000,000 IQD
Improving and developing the electricity network in Al-Sharsh area in Qurna 2014 Baghdad governorate 1,035,750,000 IQD
Improving and developing the electricity network for the eastern regions of Basra (Al-Nashwa) 2014 Baghdad governorate 1,534,225,000 IQD
Improving and developing the electricity network for the northern regions of Basra 2014 Baghdad governorate 809,400,000 IQD
Optical cable extension project 2015 Huawei Company 232,016 $
mplementation of a joint sewage network in area (893), Al-Rasheed Municipality 2017 Baghdad Municipality 608,924,500 IQD
Rehabilitation of the square for the statue of the poet Badr Shaker al-Sayyab on the Shatt al-Arab C 2017 Ministry of Culture 450,535,000 IQD
Construction of the burn center building in Al-Fayhaa General Hospital 2018 Baghdad governorate 7,556,000,000 IQD
Umm Qasr sewers and roads project, Contract No. 23 municipalities for the year 2019 2019 UAE Metito Company 44,000,000,000 IQD
Rehabilitation of Baghdad city tunnels , in the Rusafa side (Tahrir, Al-Tayaran, Muzaffar) 2019 Baghdad Municipality 2,064,735,500 IQD
Implementation of the second phase of the Basra Water Directorate building 2022 Baghdad governorate 5,480,785,000 IQD
Rehabilitation of the Tigris irrigation project 2022 Ministry of water resources-World Bank Fund 744,956 $
Construction and paving of roads in Al-Falahat and Al-Sabihat area, Fallujah district 2022 Al-Anbar governorate 1,399,000,000 IQD
Treatment of erosion occurring in the left Euphrates River with a length of 1500 m in Abu Ghraib 2022 Reconstruction Fund 4,985,478,640 IQD